Hercules Street Park construction update - March/April 2019

3 June 2019

Construction completed since our last update

  • Completion of bulk earthworks
  • Finalisation of stormwater and sewer reticulation
  • Retaining wall construction
  • Soiling of Kingsford Smith Drive gardens

Construction sequence of works for the next four weeks
  • Dog off leash fencing
  • Ex-ground tree transplanting
  • Commence formed concrete landscape walls
  • Commence irrigation